Installation of 20kV (3x630mm in trefoil and 1x Ø32 duct) and warning tape over 28km. Depths installed at are 1.8m. Ground conditions were particularly hard in places with clay and sections of deep peat. Duct installation was completed ahead of the civil contractor completing the access roads for the windfarm construction. Reducing sub-contractor interface, pinch points and overall programme of works.
Client: A-Hak
Duration: Two Months
Location: Holland
When: March / April 2019